FAQs About The New Facility
-
The EPA issued new permit limits in 2022 for ammonia, phosphorus, and metals. Our current facility, built in the early 1970s, does not meet these requirements. We must build a new facility to stay in compliance and protect our rivers and pond.
-
The upgraded Wastewater Treatment Facility will be designed for a half-century service life, using proven technology and reliable equipment.
-
The new WWTF will reduce environmental impacts through energy-efficient design, resilient systems, and advanced monitoring tools. The goal is to minimize the facility’s carbon footprint while protecting the Mad River, Corcoran Pond, and surrounding National Forest.
-
The wastewater treatment facility will protect water quality in the Mad River and Corcoran Pond, supporting recreation, tourism, and property values. It’s essential to meet federal requirements and secure state and federal support to minimize costs. The facility promotes public health, maintains local water body integrity, and enhances the recreational experience for residents and visitors. Investing in it ensures clean water and a sustainable environment for future generations.
FAQs About The Cost of the Facility
-
The town approved up to $42 million in 2020. Due to inflation, shortages, rising material and labor costs, as well as new environmental requirements, the cost has doubled.
-
Costs have risen due to inflation, materials tariffs, higher prices and shortages of labor, and stricter environmental requirements. Like other infrastructure projects nationwide, wastewater facilities are more expensive today than even a few years ago.
-
Bonding the project will increase local taxes, though Waterville Valley remains competitive compared to nearby towns. The Town will work two secure state and federal grants and low-interest loans to reduce the burden.
-
Without an upgrade, Waterville Valley will face significant EPA fines, legal risks, and the inability to support future development. Delaying the project will significantly increase costs over time.
FAQs About Construction
-
Construction could take two to three years while the existing facility continues to operate. Residents may see some traffic, equipment, and road use during this period, but the Town and contractors will work to minimize disruptions. Construction updates will be posted to this site.